Civil Engineering
Rohini College of Engineering & Technology
Sl.No | Project Details | Duration | Funding Agency | |||||||
---|---|---|---|---|---|---|---|---|---|---|
S.No | Project Details | |||||||||
1 | Mix design –high strength concrete | 2 Months | Feed Back Infra Limitted |
|||||||
1 |
|
|||||||||
2 | Material testing –Soil,cement,steel rod, water and aggregate | 3 Months | Feed Back Infra Limitted |
|||||||
2 |
|
Sl.No | Project Details | Duration | Funding Agency | |||||||
---|---|---|---|---|---|---|---|---|---|---|
S.No | Project Details | |||||||||
1 | Standard penetration test-site-1 and material testing | 3 Months | Feed Back Infra Limitted |
|||||||
1 |
|
|||||||||
2 | Standard penetration test-site-2 and material testing | 3 Months | Feed Back Infra Limitted |
|||||||
2 |
|
Sl.No | Project Details | Duration | Funding Agency | |||||||
---|---|---|---|---|---|---|---|---|---|---|
S.No | Project Details | |||||||||
1 | Design and detailing of framed structures | 6 months | SS ENGINEERING CONSTRUCTION |
|||||||
1 |
|
Sl.No | Project Details | Duration | Funding Agency | |||||||
---|---|---|---|---|---|---|---|---|---|---|
S.No | Project Details | |||||||||
1 | Design and detailing of Framed structure | 6 months | UPK TECHSERV, NAGERCOIL |
|||||||
1 |
|
Sl.No | Project Details | Duration | Funding Agency | |||||||
---|---|---|---|---|---|---|---|---|---|---|
S.No | Project Details | |||||||||
1 | Design and detailing of an Apartment building | 6 months | UPK TECHSERV, NAGERCOIL |
|||||||
1 |
|
Sl.No | Project Details | Duration | Funding Agency | |||||||
---|---|---|---|---|---|---|---|---|---|---|
S.No | Project Details | |||||||||
1 | Design and detailing of an Apartment building | 6 months | CHELLAPPA CONSTRUCTIONS |
|||||||